SCARBOROUGH – In a bid to keep residents informed and engaged, the Scarborough Subway Extension project team has been actively conducting a series of pop-up events across Scarborough. Early July saw the team set up booths at popular venues such as Scarborough Town Centre, Canadian Tire, and Taste of Lawrence, providing residents with project updates and a platform to voice their inquiries, comments, concerns, suggestions, and recommendations.
Upcoming Engagement Opportunities
The community engagement team is committed to maintaining an active presence in Scarborough and has scheduled more pop-up events for the coming weeks. Residents are encouraged to stop by, get the latest project updates, and share their feedback with the team at the following locations:
- Oriental Centre
- Address: 4438 Sheppard Ave E, Scarborough, ON M1S 5V9
- Date: July 12, 2024
- Time: 1:00 p.m. – 4:00 p.m.
- Toronto Public Library – Agincourt Branch
- Address: 155 Bonis Ave, Toronto, ON M1T 3W6
- Date: July 26, 2024
- Time: 1:00 p.m. – 4:00 p.m.
For more information on upcoming events, please click here.
Construction Updates: Progress Avenue Bridge Closure and Demolition
The Scarborough Subway Extension project is moving forward with significant infrastructure changes, including the demolition of the Progress Avenue bridge over McCowan Road to make way for the new Scarborough Centre Subway Station. The demolition work will be carried out in four stages, starting this Friday:
- Stage 1: July 12 – August 16, 2024
- Permanent ramp closure: Progress Avenue ramp and Bushby Drive ramp
- Demolition of Progress Avenue ramp and pedestrian underpass
- Stage 2: August 16, 2024
- Permanent closure of Progress Avenue bridge
- Stage 3: August 30 – September 3, 2024 (24-hour work)
- Demolition of Progress Avenue Bridge and closure of McCowan Road
- Stage 4: August 26 – September 18, 2024
- Demolition of Bushby Drive ramp and Scarborough Rapid Transit (SRT) pedestrian bridge
Work Schedule:
- Weekdays from 7 a.m. – 7 p.m.
- August 30 – September 3, 2024: 24-hour work
All schedules are approximate and subject to change. For more detailed information, please click here.
Community Feedback and Suggestions
The project team is always looking for ways to better serve the Scarborough community. If you have suggestions for future event locations or any other feedback, please reach out to us. Your input is essential in ensuring the success of the Scarborough Subway Extension project and its positive impact on the community.
Stay connected with the latest developments and join us at our upcoming events to share your thoughts and concerns. Together, we can build a better future for Scarborough.